PHPMeetingMinutes20080226
Attendees: Petr Pisl, Tomas M, Tomasz S, Leon, Petr Jiricka, Barbara, Hong, Philipp > > Agenda: > > 1. General Status > - Planning > - Development Engineering Working on PHP parser, expecting to have something that can be built on in 1-2 days. Work on Projects area can start ASAP. Work on editor can start when the infrastructure is ready. Builds by RE usable for testing expected early next week. > - HIE Working on upload/download specification. > - QE No status. > - Docs Continuing to work on web docs. Question about context help - when in build? Answer - this is not required for the April release. Web docs more important. Also, the UI will keep changing. > 2. Engineering plan review > http://wiki.netbeans.org/PHPEngineeringPlan > Reviewed. Minor changes in schedule, open issues identified. Petr J to update based on the feedback.