NetBeans 73 HighResistance

In order to better stabilize 7.3 FCS we will utilize High Resistance (HR) process.

  • HR starts on Jan 9, 2013 at 8pm CET time in 'all *-main repositories
  • release73 branch is created on Jan 10 after all recent integrations are propagated to releases clone. This branch is used only for HR integrations.
  • When release73 branch is created all *-main repositories are opened for fixes
  • Build from release73 branch is created on daily basis till RC1, then on demand
  • all P1s have to be fixed
  • all P2s reported before cut-off (Jan 9) have to be fixed or waived
  • P2s reported after cut-off are evaluated for stopper status, all stoppers are marked with P1 and fixed into release73, if such P2 is not marked as stopper it's waived for this release

Integrate bugfix - how to

  • Mark the bug with 73_HR_FIX_CANDIDATE keyword (bugs)
  • Integrate into {some}-main, change Target Milestone to Dev and ask QE for verification
  • Send email to reviewersATnetbeans.org and add following information:
  • Description of the bug (including IZ #)
  • Impact assessment i.e. why it is a showstopper?
  • Risk assessment i.e. why is it safe?
  • Confirmation of peer code review and QE verification of fix (QE adds note into comment about verification)
  • Changeset info (for reviewing diffs)
  • wait 6 hours and if there is no objection, or all questions have been answered continue with integration into release73 branch. (commits)
  • Mark the bug with 73_HR_FIX keyword (bugs) and change Target Milestone to 7.3
  • QE verifies the fix in NB 7.3 build (changes status to VERIFIED)
Not logged in. Log in, Register

By use of this website, you agree to the NetBeans Policies and Terms of Use. © 2012, Oracle Corporation and/or its affiliates. Sponsored by Oracle logo