NB701HighResistance

In order to better stabilize 7.0.1 FCS we will utilize High Resistance (HR) process.

  • HR starts on June 16th 8:00am CET time in release701 branch in releases repository
  • This branch is used only for HR integrations.
  • Build from release701 branch is created on demand
  • all P1s have to be fixed
  • all P2s reported before cut-off (June 13) have to be fixed or waived
  • P2s reported after cut-off are evaluated for stopper status, all stoppers are marked with P1 and fixed into release701, if such P2 is not marked as stopper, target milestone should be set to Dev and the bug is waived for this release automatically

Integrate bugfix - how to

  • Mark the bug with 701_HR_FIX_CANDIDATE keyword (bugs)
  • Integrate into {some}-main, change Target Milestone to Dev and ask QE for verification
  • Send email to reviewersATnetbeans.org and add following information:
  • Description of the bug (including IZ #)
  • Impact assessment i.e. why it is a showstopper?
  • Risk assessment i.e. why is it safe?
  • Confirmation of peer code review and QE verification of fix
  • Changeset info (for reviewing diffs)
  • wait 6 hours and if there is no objection, or all questions have been answered continue with integration into release701 branch. (commits)
  • Mark the bug with 701_HR_FIX keyword (bugs) and change Target Milestone to 7.0.1