NB67Milestones
NetBeans 6.7 Milestones Calendar
Milestone | Feature freeze | Promotion date | QA report | Content |
---|---|---|---|---|
6.7M1 | 2008-11-28 | 2008-12-17 | NB67Milestone1Report | New & Noteworthy M1 |
6.7M2 | 2009-02-02 | 2009-02-18 | NB67Milestone2Report | New & Noteworthy M2 |
6.7M3 | 2009-03-09 | 2009-03-23 | NB67Milestone4Report | New & Noteworthy M3 |
- The last milestone of 6.7 is M3, feature freeze for 6.7 is the feature freeze of M3.
- See also NB67QualityCriteria
The same set of Target Milestones were created in NetBeans Issuezilla, e.g. 6.7M1. Developer should mark their issues which they plan to be completed at a certain milestone using this field.
Critical Release Dates
- Dec 17 - NB 6.7 *Milestone 1 Release*
- Feb 18 - NB 6.7 *Milestone 2 Release*
- Mar 23 - NB 6.7 *Milestone 3 Release*
- Mar 23 - NB 6.7 *Feature Freeze*
- Apr 20 - NB 6.7 *Beta Release*
- May 11 - NB 6.7 *UI Freeze*
- May 25 - NB 6.7 *Code Freeze*
- Jun 01 - NB 6.7 *RC 1 Release*
- Jun 08 - NB 6.7 *RC 2 Release*
- Jun 22 - NB 6.7 *Final Release* (date still TBD)