NB 6.0.1 Key Milestones and Deliverables

Name Planned_Date Boundary_Date Actual_Finish Notes
Go/NoGo RC2, branding integrated, build FCS (RC2+translated files) started Wed, Jan 23 Wed, Jan 23 Wed, Jan 23
Installer sanity check Fri, Jan 25 Fri, Jan 25 Fri, Jan 25
BE posts those bits, web team stages Tue, Jan 29 Fri, Feb 1 Fri, Feb 1
Sanity check on the staged web site, fixing issues Wed, Jan 30 Fri, Feb 1 Fri, Feb 1
Go/NoGo for FCS Wed, Jan 30 Fri, Feb 1 Fri, Feb 1
Web team pushes NB 6.0.1 FCS live Thur, Jan 31 Thu, Feb 7 as of 6 Feb expected to go live Close of Business Prague day