6.1M2
Detailed NetBeans 6.1 Milestone 2 / Beta schedule
| Date | Milestone | Notes |
|---|---|---|
| Feb/25 | M2/Beta Feature freeze | Stabilization week started, 8am UTC |
| Feb/28 | M2/Beta cut-off date - Opened P2s | P2s reported after this date are not counted into Quality Criteria for M2/Beta |
| Feb/29 | QE testing completed | Appropriate QE managers should fill report before Feb/29 COB |
| Mar/3 | release61-m2 clone created by BE, HR starts - rules | Only Milestone stoppers would be fixed in this clone. |
| Mar/3 | Beta branding integrated | See the branding checklist |
| Mar/3 | Build from the milestone clone is ready for testing | The build should be available afternoon Prague time. |
| Mar/3 | Bits are staged on internal staging site which is ready for review (both content and download page) | Afternoon Prague time. |
| Mar/4 | Sanity testing by QE | Final Go/No Go |
| Mar/5 | Release and announcement on nbusers | |